  9. Space Digest                Sat, 19 Dec 92       Volume 15 : Issue 568
  10.  
  11. Today's Topics:
  12.                       : Relay to Follow Galileo?
  13.                      Aerospike engines/SSTO/DC-?
  14.                                 Aurora
  15.              Chicken Guns (was Re: "trivial engineering")
  16.                            DoD launcher use
  17.                               EVA costs
  18.                Galileo Update - 12/08/92 (Earth Flyby)
  19.                       Galileo Update - 12/18/92
  20.                  Justification for the Space Program
  21.                        Mach 8+ Space/Spy Plane?
  22.     MOL (was Re: Terminal Velocity of DCX? (was Re: Shuttle ...))
  23.                   Relay to follow Galileo? (3 msgs)
  24.                             Space Tourism
  25.                                  SPAN
  26.                       SSTO Concepts FAQ (2 msgs)
  27.            Terminal Velocity of DCX? (was Re: Shuttle ...)
  28.  
  29.     Welcome to the Space Digest!!  Please send your messages to
  30.     "space@isu.isunet.edu", and (un)subscription requests of the form
  31.     "Subscribe Space <your name>" to one of these addresses: listserv@uga
  32.     (BITNET), rice::boyle (SPAN/NSInet), utadnx::utspan::rice::boyle
  33.     (THENET), or space-REQUEST@isu.isunet.edu (Internet).
  34. ----------------------------------------------------------------------
  35.  
  36. Date: 18 Dec 92 16:17:24 GMT
  37. From: Curtis Roelle <roelle@uars_mag.jhuapl.edu>
  38. Subject: : Relay to Follow Galileo?
  39. Newsgroups: sci.space
  40.  
  41. BrianT@cup.portal.com (Brian Stuart Thorn) writes:
  42.  
  43. >The folding, umbrella-type antennae have been used at least ten times
  44. >in space (that is, two each on TDRS-A, TDRS-C, TDRS-D, and TDRS-E, one
  45. >on ATS-6 (late-70s pathfinder comsat) and one on Galileo.
  46. >Only the one on Galileo failed to open on command, and there is still
  47. >hope it will be coaxed open. (They haven't tried brute force yet.)
  48.  
  49. >Lesson:  OPEN THE DAMNED ANTENNA IMMEDIATELY AFTER LAUNCH!!!
  50.  
  51. And again writes,
  52.  
  53. >  Ryan...
  54. >   
  55. >  Galileo's umbrella-type High Gain Antenna was left in the folded
  56. >  position because it was thought that the high temperatures it would
  57. >  encounter during the Venus flyby portion of the mission could warp
  58. >  the antenna. They attempted to open the antenna only after the Venus
  59. >  flyby, when Galileo flew farther from the Sun. It was jammed.
  60.    
  61. >  Cassini, I think, will have a standard hard HGA, similar to the
  62. >  Voyager and Magellan antennae. I hope the Galileo problem does not
  63. >  prevent future spacecraft from using the folding antenna design. It
  64. >  worked quite well on the TDRS satellites.
  65. >  
  66. >  -Brian
  67.  
  68. Is there a possiblity that, despite Galileo's HGA parasol, solar heat
  69. could have still been a factor in its failure to deploy?  Especially
  70. when one considers that for the nine successful deployments out of
  71. ten, cited above, every corresponding spacecraft never left earth
  72. orbit, while Galileo got as close to the sun as the planet Venus.
  73.  
  74. Curt
  75.  
  76. ------------------------------
  77.  
  78. Date: Fri, 18 Dec 1992 16:01:32 GMT
  79. From: Edmund Hack <arabia!hack>
  80. Subject: Aerospike engines/SSTO/DC-?
  81. Newsgroups: sci.space
  82.  
  83. There has been a lot of speculation as to the reasons why the SDIO SSRT 
  84. program  is not using the aerospike engine for propulsion as originally
  85. envisioned by the SSTO proponents in the 60s and later.
  86.  
  87. I saw a summary of the report done by The Aerospace Co. for the Air Force on
  88. the SSX proposal that was made by Max Hunter, et.al.  This proposal was
  89. the one that lead to the SSRT program being started by SDIO.
  90.  
  91. A couple of caveats emerged concerning the SSX design that were felt to be
  92. potential show stoppers in meeting the SSX goals, all related to the 
  93. use of aerospike engines.  First, the "engine first" reentry profile 
  94. required active cooling of the heat shield/engine plug assembly.  It was
  95. felt that this complicated plumbing could be a nightmare to repair if
  96. a leak developed and hindered access to part of the structure.  Since
  97. low maintenance was a goal of SSX, this was considered a risk.  Second,
  98. no aerospike engine of the size  proposed had ever been built, much
  99. less tested.  This was also a risk, as "simple scaling" of rocket engines
  100. is an oxymoron.  Third, the exact performance characteristics of
  101. aerospike engines at high thrust and multiple altitudes are somewhat
  102. unknown.  The aerospike work NASA had funded had limited data from
  103. vacuum tests, concentrated on lower thrust engines (since the test
  104. stands at Lewis? in the vacuum chambers can only evacuate a limited
  105. amount of exhaust products).  Given the uncertainty about large aerospikes,
  106. I'd agree that they are a risky choice with multiple points of failure. 
  107. My opinion is that Marshall or Lewis ought to be working on them (as well
  108. as ion engines, arcjets (although DOD may fly some soon), solar sails,
  109. and nuclear thermal engines) right now, rather than only trying to tweak an
  110. additional 3 Isp out of H2O2 engines. 
  111.  
  112. The study was cautiously favorable to SSX, recommending use of conventional
  113. engines if possible, and watching weight margins carefully.  (The major
  114. warning was that if the mass of the vehicle rose only slightly from
  115. projections, the useful payload would be wiped out.  From what I have
  116. seen, the DC-X team is very aware of this.)
  117.  
  118. I would also like to second Bill Higgins' call for the SSTO 
  119. "discussion" to be calmed down a bit. There has been more heat than
  120. light generated recently.  It is pointless to argue about what the
  121. DC-? can or can't do at this point.  Let's watch the DC-X flight this
  122. spring and lobby, lobby, lobby for more money.
  123.  
  124. -- 
  125. Edmund Hack - Lockheed Engineering & Sciences Co. - Houston, TX
  126. hack@aio.jsc.nasa.gov - I speak only for myself, unless blah, blah..
  127. "You know, I think we're all Bozos on this bus."
  128. "Detail Dress Circuits" "Belt: Above A, Below B" "Close B ClothesMode"
  129.  
  130. ------------------------------
  131.  
  132. Date: 18 Dec 92 13:05:56 GMT
  133. From: Del Cotter <mt90dac@brunel.ac.uk>
  134. Subject: Aurora
  135. Newsgroups: sci.space
  136.  
  137. In article <STEINLY.92Dec16152132@topaz.ucsc.edu> Steinn Sigurdsson writes:
  138. >In article <BzCzo5.76z.1@cs.cmu.edu> nickh@CS.CMU.EDU (Nick Haines) writes:
  139. >
  140. >   Assuming that it's launching from the continental USA. Seems much more
  141. >   likely to me (given the sightings over the Netherlands as well) that
  142. >   one of the long-runway US bases in the UK or Germany is `home' to an
  143. >   Aurora.
  144. >
  145. >Nah, not isolated enough, rumour seems to be that the forward
  146. >base is a US NATO base in Scotland. 
  147.  
  148. Yes, Scotland's still in the UK at time of writing...
  149.  
  150. (What's a US NATO base?)
  151.  
  152. -- 
  153.  ',' ' ',','  |                                                  |  ',' ' ',','
  154.    ', ,','    |       Del Cotter       mt90dac@brunel.ac.uk      |    ', ,','  
  155.      ','      |                                                  |      ','    
  156.  
  157. ------------------------------
  158.  
  159. Date: 18 Dec 92 18:15:34 GMT
  160. From: Pat <prb@access.digex.com>
  161. Subject: Chicken Guns (was Re: "trivial engineering")
  162. Newsgroups: sci.space
  163.  
  164. The F-16 in the early 80's was having a real problem with bird strikes
  165. fracturing the canopies, so i heard for a while the air force
  166. was launching Frozen turkeys and chickens at the aircraft
  167. to test canopies.  i guess the frozen bit was to make the birds
  168. harder.
  169.  
  170. it was a tidbit in the paper.
  171.  
  172. ------------------------------
  173.  
  174. Date: 18 Dec 1992 00:16:37 GMT
  175. From: steve hix <fiddler@concertina.Eng.Sun.COM>
  176. Subject: DoD launcher use
  177. Newsgroups: sci.space
  178.  
  179. >In article <1992Dec14.221347.3359@iti.org> aws@iti.org (Allen W. Sherzer) writes:
  180. >
  181. >>I don't think much if any recon was flown [ in Iraq]. 
  182. >>The Air Force had better things to do with its aircraft.
  183.  
  184. What do you call a military force in combat who doesn't conduct recon
  185. (having better things to do)?
  186.  
  187. The loser.
  188.  
  189. --
  190. -------------------------------------------------------
  191. | Some things are too important not to give away      |
  192. | to everybody else and have none left for yourself.  |
  193. |------------------------ Dieter the car salesman-----|
  194.  
  195. ------------------------------
  196.  
  197. Date: 18 Dec 92 14:48:17 GMT
  198. From: begley@l14h13.jsc.nasa.gov
  199. Subject: EVA costs
  200. Newsgroups: sci.space
  201.  
  202. In article <BzFxGA.xC.1@cs.cmu.edu> roberts@cmr.ncsl.nist.gov (John Roberts)
  203. writes:
  204. >While it wouldn't be fair to divide the cost of an entire Shuttle mission
  205. >by maximum EVA time to get US EVA costs, I expect a more reasonable
  206. >accounting method would still get a figure up in the millions of dollars
  207. >per hour. Don't the EVA suits have a certain maximum number of hours they
  208. >can be used per flight?
  209. >John Roberts
  210. >roberts@cmr.ncsl.nist.gov
  211. >
  212.    The suits have about 7 hours of oxygen in their primary O2 tanks,
  213. and about the same amount in their secondary tanks under normal use
  214. conditions.  But since the secondary tanks are meant to serve as
  215. a supplement should the suit get a leak or the primary system fail,
  216. this does not give the astronaut 14 hours of oxygen.  The real limiting
  217. consumable is battery life, about 8 hours.  But this limit is for each
  218. EVA.  Once the suits are hooked up to the orbiter, the oxygen, water, and
  219. batteries are filled and recharged.  (The secondary O2 tanks are not 
  220. rechargable because they have 3 times the pressure as the primary tanks.)
  221.  
  222. ------------------------------
  223.  
  224. Date: 18 Dec 1992 14:57:53 +1100
  225. From: Mike Robson <jmr@cs.anu.edu.au>
  226. Subject: Galileo Update - 12/08/92 (Earth Flyby)
  227. Newsgroups: sci.space
  228.  
  229. baalke@kelvin.jpl.nasa.gov (Ron Baalke) writes:
  230.  
  231. >Forwarded from Bill O'Neil, Galileo Project Manager
  232.  
  233. >                            GALILEO STATUS REPORT
  234. >                                Earth Flyby
  235. >                              December 8, 1992
  236.  
  237. >     The Galileo Spacecraft is operating normally in the dual-spin mode and
  238. >is transmitting coded telemetry at 115.2 Kbps (115,200 bits/second).
  239.  
  240. >     Yesterday, part 2 of the EE-11 Earth encounter memory load sequence
  241. >was uplinked.  Moon closest approach occurred at approximately 7:58 PM PST.
  242.  
  243. [...]
  244.  
  245. >     Today, December 8, 1992, Earth closest approach occurred at approximately
  246. >7:09 AM PST.  Real-time commands are being sent to enable the Sun algorithms,
  247. [...]
  248.  
  249. 11 hours and 11 minutes from the moon to the earth! Is this a record?
  250.  
  251. ------------------------------
  252.  
  253. Date: Sat, 19 Dec 1992 01:12:13 GMT
  254. From: Ron Baalke <baalke@kelvin.jpl.nasa.gov>
  255. Subject: Galileo Update - 12/18/92
  256. Newsgroups: sci.space,sci.astro,alt.sci.planetary
  257.  
  258. Forwarded from Neal Ausman, Galileo Mission Director
  259.  
  260.                                    GALILEO
  261.                       MISSION DIRECTOR STATUS REPORT
  262.                                 POST-LAUNCH
  263.                           December 11 - 17, 1992
  264.          *************************************************************
  265.                    Merry Christmas and Happy New Year!!
  266.  
  267.          Because of the Christmas Holiday, the Mission Director Report
  268.          will not be published next week.  The next report will be on
  269.          January 7, 1992.
  270.  
  271.          *************************************************************
  272.  
  273. SPACECRAFT
  274.  
  275. 1.  On December 11, real-time commands were sent to turn ranging off in order
  276. to maximize the downlink telemetry performance for the science instrument
  277. calibration activities scheduled later in the day.
  278.  
  279. 2.  On December 12, real-time commands were sent to zero out the Bright Body
  280. Avoidance (BBA) vector onboard the spacecraft.  This vector was causing the
  281. star scanner shutter to close sooner than expected resulting in infrequent
  282. dropouts of the first star in a two star set.  This action was taken to
  283. eliminate the possibility of the star dropouts increasing and causing SEQID
  284. to fail which in turn would have caused the gyros to be selected as the
  285. primary attitude source and would have adversely effected scan platform
  286. priority and the possibility of tripping gyro fault protection.
  287.  
  288. 3.  On December 12, real-time commands were sent to turn Two-Way Noncoherent
  289. (TWNC) on prior to the sequence controlled Extreme Ultraviolet Spectrometer
  290. (EUV)/Ultraviolet Spectrometer (UVS) cross calibration activity.
  291.  
  292. 4.  On December 13, the spacecraft went through perihelion at a solar distance
  293. of .982 AU.  All spacecraft temperatures were near predicted levels.
  294.  
  295. 5.  On December 14, a NO-OP command was sent to reset the command loss timer
  296. to 264 hours, its planned value during this mission phase.
  297.  
  298. 6.  On December 14, a routine sun vector update was performed.  This sun
  299. vector is valid until December 31, 1992.
  300.  
  301. 7.  On December 15, real-time commands were sent to disable the attitude
  302. control bright body avoidance fault protection after the completion of the
  303. Earth 2 flyby.
  304.  
  305. 8.  On December 15, real-time commands were sent to turn the TWNC off prior
  306. to the SITURN on December 16 in order to receive two-way doppler data for
  307. navigation purposes.
  308.  
  309. 9.  On December 16, the spacecraft executed a 14-degree SITURN which brought
  310. the cone angle down from approximately 95 degrees to 83 degrees.  Subsequently,
  311. the telecommunication performance improved prior to the Earth/Moon conjunction
  312. movie playback beginning on December 17 and continuing into December 19.
  313.  
  314. 10. On December 16, the Galileo Optical Communications Experiment from an
  315. Earth-based Xmitter (GOPEX) experiment was completed.  This experiment
  316. consisted of pulsing a laser at the Galileo spacecraft from the Table Mountain
  317. Observatory (TMO) and the Starfire Optical Range (SOR).  The Solid State
  318. Imaging (SSI) camera was shuttered while slewing across the Earth resulting
  319. in a series of illuminated pixels in the image.  Initial results indicate that
  320. laser transmissions were successfully detected from both TMO and SOR.  Data
  321. analysis is continuing.
  322.  
  323. 11. On December 17, real-time commands were sent at the direction of the PI
  324. (Principal Investigator) to turn the Plasma Detector (PLS) instrument off
  325. approximately 31 hours before the stored sequence onboard the spacecraft
  326. would have turned the instrument off.  The instrument temperature at turn off
  327. was approximately 43.7 degrees C which was less than one degree below the
  328. maximum waived temperature limit of 44.4 degrees C.
  329.  
  330. 12. During the reporting period, numerous science instrument
  331. calibrations/characterization activities were performed to take advantage of
  332. the high telemetry data rates while close to the Earth.  Activities included
  333. Near Infrared Mapping Spectrometer (NIMS) partial Photometric Calibration
  334. Target (PCT) calibration, NIMS partial Radiometric Calibration Target (RCT)
  335. calibration, Extreme Ultraviolet Spectrometer (EUV)/Ultraviolet Spectrometer
  336. (UVS) cross calibration, EUV star calibration, UVS syscan, NIMS mirror scan
  337. calibration, Plasma Wave (PWS) calibration, and Solid State Imaging (SSI)
  338. partial PCT.  All calibration/characterization activities were performed
  339. nominally and data analysis is in progress.
  340.  
  341. 13. The AC/DC bus imbalance measurements exhibited some change. The AC
  342. measurement has ranged from 13DN to 17DN and now reads 17DN (3.9 volts).
  343. The DC measurement has ranged from 44DN (4.7 volts) to 157DN (18.5 volts) and
  344. now reads 157DN (18.5 volts).  These measurement variations are consistent
  345. with the model developed by the AC/DC special anomaly team.
  346.  
  347. 14. The Spacecraft status as of December 17, 1992, is as follows:
  348.  
  349.        a)  System Power Margin -  79 watts
  350.        b)  Spin Configuration - Dual-Spin
  351.        c)  Spin Rate/Sensor - 3.15 rpm/Star Scanner
  352.        d)  Spacecraft Attitude is approximately 6 degree
  353.            off-sun (leading) and 83 degrees off-earth (leading)
  354.        e)  Downlink telemetry rate/antenna- 1200bps(coded)/LGA-1
  355.        f)  General Thermal Control - all temperatures within
  356.            acceptable range
  357.        g)  RPM Tank Pressures - all within acceptable range
  358.        h)  Orbiter Science- all instruments are powered on
  359.            except the PPR, NIMS, and PLS
  360.        i)  Probe/RRH - powered off, temperatures within
  361.            acceptable range
  362.        j)  CMD Loss Timer Setting - 264 hours
  363.            Time To Initiation - 240 hours
  364.  
  365.  
  366. UPLINK GENERATION/COMMAND REVIEW AND APPROVAL:
  367.  
  368. 1.  The EE-12 (Earth-Earth 12) Preliminary Sequence and Command Generation
  369. products were approved by the Project on December 16, 1992.  This sequence
  370. covers spacecraft activities from January 20, 1993 to January 23, 1993 and
  371. from February 8, 1993 to April 12, 1993.
  372.  
  373. 2.  The Dual Drive Actuator (DDA-5) Part A sequence memory load was approved
  374. for transmission by the Project on December 17, 1992.  This sequence covers
  375. High Gain Antenna (HGA) motor hammering activities from December 28, 1992
  376. through January 4, 1993.  Part B of this sequence will be reviewed for
  377. approval on December 30, 1992, subsequent parts of the overall DDA-5 sequence
  378. will be reviewed and approved as needed after January 4, 1993.  The commands
  379. for windup/hammering activities on December 29 and 30 were also reviewed.
  380. Individual sets of hammering/windup commands will be approved as required
  381. immediately prior to being uplinked to the spacecraft.
  382.  
  383.  
  384. TRAJECTORY
  385.  
  386.      As of noon Thursday, December 17, 1992, the Galileo Spacecraft trajectory
  387. status was as follows:
  388.  
  389.     Distance from Earth         6,928,300 km (.05 AU)
  390.     Distance from Sun           147,267,200 km (0.99 AU)
  391.     Heliocentric Speed          140,300 km per hour
  392.     Distance from Jupiter       836,434,500 km
  393.     Round Trip Light Time       0 minutes, 48 seconds
  394.  
  395. SPECIAL TOPIC
  396.  
  397. 1.  As of December 17, 1992, a total of 8815 real-time commands have been
  398. transmitted to Galileo since Launch.  Of these, 3768  were initiated in the
  399. sequence design process and 5047 initiated in the real-time command
  400. process.  In the past week, 29 real time commands were transmitted: 15 were
  401. initiated in the sequence design process and 14 initiated in the real time
  402. command process.  Major command activities this week included commands to
  403. turn ranging off, zero out the bright body vector, turn the TWNC on, reset
  404. the command loss timer, turn the TWNC off, disable the bright body avoidance
  405. fault protection, and turn the PLS instrument off.
  406.      ___    _____     ___
  407.     /_ /|  /____/ \  /_ /|     Ron Baalke         | baalke@kelvin.jpl.nasa.gov
  408.     | | | |  __ \ /| | | |     Jet Propulsion Lab |
  409.  ___| | | | |__) |/  | | |__   M/S 525-3684 Telos | Choose a job you love, and
  410. /___| | | |  ___/    | |/__ /| Pasadena, CA 91109 | you'll never have to work
  411. |_____|/  |_|/       |_____|/                     | a day in you life. 
  412.  
  413. ------------------------------
  414.  
  415. Date: Fri, 18 Dec 92 07:37:31 GMT
  416. From: Felix Gorney Mfg 4-6983 <gorney@picard.med.ge.com>
  417. Subject: Justification for the Space Program
  418. Newsgroups: alt.rush-limbaugh,talk.politics.space,sci.space
  419.  
  420. : |>      Can any of you think of any moral or philosophical justification
  421. : |>     for using huge amounts of taxpayer money to fund the "space
  422. : |>     program" at all?  Not counting, of course, it provides high-
  423. : |>     pay, high-tech jobs for a bunch of us.
  424. :
  425.  
  426.  
  427. This country does not do enough basic research as it is. The space 
  428. program, and the defense department have done a great deal of this. 
  429. Their research has led to such things as the computers we are using. 
  430. The first electronic computers were developed by the military. I
  431. beleive they were using them to crack codes. 
  432.  
  433. Felix Gorney
  434.  
  435.  
  436.  
  437. ------------------------------
  438.  
  439. Date: Fri, 18 Dec 1992 05:39:17 GMT
  440. From: Robin Kenny <robink@hparc0.aus.hp.com>
  441. Subject: Mach 8+ Space/Spy Plane?
  442. Newsgroups: sci.aeronautics,sci.space
  443.  
  444. AUJAM@ASUACAD.BITNET () writes:
  445. : In article <1992Dec11.002726.712137@locus.com>, rich@locus.com (Rich (the Wiz)
  446. : Silva) says:
  447. : >
  448. : >    Apparently reported in some English Aeronautic Journal was
  449. : >    a story claiming that the US has a new spy plane capable of
  450. : >    Mach 8+ (at least) in test.  Apparently said plane has a
  451. :      [ ... ] 
  452. : I was in Joshua Tree national forest last May when I saw a plane in the upper
  453. : atmosphere fly across the sky about as fast as metors do I didn't here any
  454. : sonic booms but I't couldn't have been a jet airliner it was moving too fast
  455. : I did notice it's contrail was lumpy like -+-+-+-+-+-+ like a pulse.
  456.                                             ^^^^^^^^^^^^
  457. Popular Science magazine had a photograph of a "mysterious" contrail that
  458. looks like -+-+-+-+-+-+, and very thin compared to other trans-sonics.
  459. This was ?September 1992 (this year anyway)
  460. : >--
  461. : >Rich Silva
  462. : >Locus Computing Corporation                rich@LOCUS.COM
  463. : >                  {uunet,ucivax,trwrb}!lcc!rich
  464. : >       {randvax,ucbvax,trwspp}!ucla-se!lcc!rich
  465.  
  466. Robin Kenny - nope; nothing to do with where I work and completely my own
  467.               opinions (not my employer's)  Couldn't you tell by the content?
  468.               --------------------------------------------------------------
  469.  
  470. ------------------------------
  471.  
  472. Date: Fri, 18 Dec 1992 10:44:41 GMT
  473. From: Hartmut Frommert <phfrom@nyx.uni-konstanz.de>
  474. Subject: MOL (was Re: Terminal Velocity of DCX? (was Re: Shuttle ...))
  475. Newsgroups: sci.space
  476.  
  477. ewright@convex.com (Edward V. Wright) writes:
  478.  
  479. >You heard wrong.  One MOL flew (unmanned).
  480.  
  481. Could somebody provide data ?
  482. -
  483.  Hartmut Frommert                 <phfrom@nyx.uni-konstanz.de>
  484.  Dept of Physics, Univ of Constance, P.O.Box 55 60, D-W-7750 Konstanz, Germany
  485.                                            -- Eat whale killers, not whales --
  486.  
  487. ------------------------------
  488.  
  489. Date: Fri, 18 Dec 92 08:33:48 EST
  490. From: John Roberts <roberts@cmr.ncsl.nist.gov>
  491. Subject: Relay to follow Galileo?
  492.  
  493. -From: M22079@mwvm.mitre.org
  494. -Subject: Re: Relay to Follow Galileo?
  495. -Date: 17 Dec 92 18:25:13 GMT
  496. -Organization: The MITRE Corporation, McLean VA 22102
  497.  
  498. -     I would like to see the math that shows that TDRS could not be sent to
  499. -Jupiter, remember that a TDRS has relatively large fuel tanks, in addition to
  500. -fuel in the IUS.
  501.  
  502. I expect that the TDRS satellites have only very small rocket engines,
  503. intended for slow maneuvering and stationkeeping. It might take a stronger
  504. thrust over a shorter period of time to insert it into Jupiter orbit.
  505.  
  506. John Roberts
  507. roberts@cmr.ncsl.nist.gov
  508.  
  509. ------------------------------
  510.  
  511. Date: Fri, 18 Dec 1992 14:32:01 GMT
  512. From: fisher@decwin.enet.dec.com
  513. Subject: Relay to follow Galileo?
  514. Newsgroups: sci.space
  515.  
  516. It seems to me that there is a lot of stuff that people have not thought of 
  517. regarding sending a TDRSS after Galileo.  For example, I'm not sure you can
  518. just splice in an RTG in place of solar panels.  Are they the right voltage?
  519. Power?  How about mass distribution and other dynamic considerations?  Are the
  520. thrusters placed correctly now?
  521.  
  522. How about the thermal environment during the cruise and Jovian orbit?  TDRSS
  523. was designed for the environment of Earth orbit (in particular, Clarke (geo-
  524. synchronous) Earth orbit.
  525.  
  526. Someone already pointed out the Jupiter insertion burn may need to be higher
  527. thrust/shorter duration than the station keeping engines can provide.  I
  528. suppose
  529. it is conceivable that the Apogee kick motor might be better suited, but I
  530. doubt it given the relative gravity (and thus the incoming probe velocity) at
  531. Jupiter.
  532.  
  533. Burns
  534.  
  535. ------------------------------
  536.  
  537. Date: 18 Dec 92 23:44:07 GMT
  538. From: Ron Baalke <baalke@kelvin.jpl.nasa.gov>
  539. Subject: Relay to follow Galileo?
  540. Newsgroups: sci.space
  541.  
  542. In article <1992Dec18.143201.10326@nntpd.lkg.dec.com>, fisher@decwin.enet.dec.com () writes...
  543. >It seems to me that there is a lot of stuff that people have not thought of 
  544. >regarding sending a TDRSS after Galileo.  For example, I'm not sure you can
  545. >just splice in an RTG in place of solar panels.  Are they the right voltage?
  546. >Power?  How about mass distribution and other dynamic considerations?  Are the
  547. >thrusters placed correctly now?
  548.  
  549. One other consideration is that the satellite would have to be radiation
  550. hardened to survive in the strong radiation belts surrounding Jupiter. 
  551.      ___    _____     ___
  552.     /_ /|  /____/ \  /_ /|     Ron Baalke         | baalke@kelvin.jpl.nasa.gov
  553.     | | | |  __ \ /| | | |     Jet Propulsion Lab |
  554.  ___| | | | |__) |/  | | |__   M/S 525-3684 Telos | Choose a job you love, and
  555. /___| | | |  ___/    | |/__ /| Pasadena, CA 91109 | you'll never have to work
  556. |_____|/  |_|/       |_____|/                     | a day in you life. 
  557.  
  558. ------------------------------
  559.  
  560. Date: 17 Dec 92 14:27:01 GMT
  561. From: clements@vax.ox.ac.uk
  562. Subject: Space Tourism
  563. Newsgroups: sci.space
  564.  
  565. In article <BzDCqA.3sI@brunel.ac.uk>, mt90dac@brunel.ac.uk (Del Cotter) writes:
  566. > It wasn't Duncan (though he was there) but Patrick Collins, of the
  567. > School of Management, Imperial College.  He wrote an article on the
  568. > subject in Analog about the same time.  He now works in Japan and has
  569. > an email address, but I haven't got it yet.
  570.  
  571.  
  572. More of interest, Pat is working on *Space Tourism* in Japan.
  573.  
  574. Guess who'll have the furst space hotel?
  575.  
  576. >    ', ,','    |       Del Cotter       mt90dac@brunel.ac.uk      |    ', ,','  
  577. -- 
  578. ================================================================================
  579. Dave Clements, Oxford University Astrophysics Department
  580. ================================================================================
  581. clements @ uk.ac.ox.vax            |  Umberto Eco is the *real* Comte de
  582. dlc      @ uk.ac.ox.astro        |           Saint Germain...
  583. ================================================================================
  584.  
  585. ------------------------------
  586.  
  587. Date: Fri, 18 Dec 1992 01:18:49 GMT
  588. From: Bruce Shetler <bvs@photon.com>
  589. Subject: SPAN
  590. Newsgroups: sci.space
  591.  
  592. Apparently there is something called the Space Physics Analysis
  593. Network.  Does anyone out there have knowledge of this net, how to
  594. access it, etc.?  Feel free to reply here or via e-mail.  
  595.  
  596. Thank you,
  597. Bruce
  598.  
  599. --
  600.  
  601. ========================================================================
  602.   Bruce Shetler                           
  603.   Photon Research Associates          Living in Southern California...
  604.   San Diego, CA   92121               The ultimate oxymoron?
  605.   bvs@photon.com        
  606. ========================================================================
  607.  
  608. ------------------------------
  609.  
  610. Date: 17 Dec 92 18:37:40
  611. From: Steinn Sigurdsson <steinly@topaz.ucsc.edu>
  612. Subject: SSTO Concepts FAQ
  613. Newsgroups: sci.space
  614.  
  615. In article <1992Dec18.012552.10183@cs.rochester.edu> dietz@cs.rochester.edu (Paul Dietz) writes:
  616.  
  617.  
  618.    In article <STEINLY.92Dec17154113@topaz.ucsc.edu> steinly@topaz.ucsc.edu (Steinn Sigurdsson) writes:
  619.  
  620.    >to handle the fuelling. Consensus was LOX/LH2 trucks carried
  621.    >about 3 tons, we need 300 tons total - that's 100 trips
  622.  
  623.  
  624.    That's wrong -- the figure was that LH2 tankers carry 3 to 5
  625.    tons, but we said nothing about LOX tankers.  LOX is much more dense
  626.    than LH2, and most of the mass of the propellant is LOX.
  627.  
  628. Ok, I can believe that - factor about 15 in fact from CRC,
  629. so we're looking at 3 ton LH2 trucks and 30 ton LOX trucks?
  630.  - I presume if you go much over 30 tons weight you're looking
  631. at new more expensive trucks (what does KSC use?).
  632.  
  633. Now, DC-1 wants something like 300 tons total, so 75 tons LH2
  634. and 225 tons LOX? That's still 30 fuel trips, maybe doable with
  635. three shifts in 24 hours, but I don't think you can do it in 8 hours?
  636. Not with one crew.
  637.  
  638. What mass flow rates do LOX and LH2 pumps use? eg the KSC ones?
  639.  
  640. |  Steinn Sigurdsson    |I saw two shooting stars last night        |
  641. |  Lick Observatory    |I wished on them but they were only satellites    |
  642. | steinly@lick.ucsc.edu |Is it wrong to wish on space hardware?        |
  643. | "standard disclaimer"    |I wish, I wish, I wish you'd care - B.B. 1983    |
  644.  
  645. ------------------------------
  646.  
  647. Date: Fri, 18 Dec 1992 02:59:23 GMT
  648. From: Paul Dietz <dietz@cs.rochester.edu>
  649. Subject: SSTO Concepts FAQ
  650. Newsgroups: sci.space
  651.  
  652. In article <STEINLY.92Dec17183740@topaz.ucsc.edu> steinly@topaz.ucsc.edu (Steinn Sigurdsson) writes:
  653.  
  654.  >Now, DC-1 wants something like 300 tons total, so 75 tons LH2
  655.  >and 225 tons LOX? That's still 30 fuel trips, maybe doable with
  656.  >three shifts in 24 hours, but I don't think you can do it in 8 hours?
  657.  >Not with one crew.
  658.  
  659. You mixture ratios are off.  The oxygen/hydrogen mixture ratio
  660. in the SSME is 6; in the Saturn J-2, 5.5.  At a ratio of 6
  661. this would be about 43 tons of hydrogen and 257 of oxygen.
  662. About 20 trips.
  663.  
  664. However, the launcher would almost certainly have fuels piped to it
  665. directly from remote storage tanks, as NASA currently does at the
  666. shuttle pads.
  667.  
  668.     Paul
  669.  
  670. ------------------------------
  671.  
  672. Date: 18 Dec 92 17:53:17 GMT
  673. From: Pat <prb@access.digex.com>
  674. Subject: Terminal Velocity of DCX? (was Re: Shuttle ...)
  675. Newsgroups: sci.space
  676.  
  677. In article <71781@cup.portal.com> BrianT@cup.portal.com (Brian Stuart Thorn) writes:
  678. >>>In the history of spaceflight, that has seldom been the case.
  679. >>
  680. >>True, but that has far more to do with the design process we use for
  681. >>spacecraft. Shuttle is the most complex vehicle ever built according
  682. >>to NASA PR (I have no idea just why NASA thinks that is worth boasting
  683. >>about). There is no reason to think that building for simplicity won't
  684. >>work. That is why everybody who has studied the problem believes that
  685. >>a SSTO can be built either now or in the near future. Even NASA internal
  686. >>assessments say it can be done.
  687. >>
  688. >>  Allen
  689. >
  690. > That it can be done, I am more or less with you. (But I fully expect
  691. > a design problem or two to slow things down...) That it can be done
  692. > at the price you quote, that's another story. Say I'm from Missouri.
  693. > Show me.
  694. > -Brian
  695. >  
  696.  
  697.  
  698.  
  699. I believe in point of fact, that is the whole point of the DC-Y.
  700. DC-X will prove the operations and technology.  DC-Y will push the
  701. envelope to LEO, and test the new engines.  DC-1 is then production.
  702.  
  703. Given the low cost of the DC-X,Y test program, we should be advocating
  704. the completion of the test program.  If it succeeds,  then we should
  705. all feel good.  if it costs too much,  we should head back to the
  706. drawing boards.  God knows,  maybe HTHL is the way to go for cheap
  707. space flight and gary gets to say "I told you so"  1x10(6) times.
  708.  
  709.  
  710.  
  711.  
  712. My gut feel, is that SSTO will always be cheaper then Stacked rockets.
  713. Now if there is some way to get useful payload to orbit in an SSTO,
  714. we will see.
  715.  
  716. ------------------------------